Leeds City Council will be carrying out resurfacing works at the junction of Otley Rd, Shaw Ln and St Annes Rd in Headingley.
The works would be done in two phases:
- Phase 1 – resurfacing of St Annes Service Road which will take place from Monday 5th June 2023 to Monday 12th June 2023 and the closure will be in place between 08:00 – 15:30. The affected businesses has been consulted.
- Phase 2 – resurfacing of the Junction of Otley Road, Shaw Lane and St Anne’s Road will take place from Monday 12th June to Friday 16th June. The closure will be in place between 23:00 and 06:00 hrs for four nights. There would also be temporary multiway lights in place from 19:00 – 23:00 each night to allow for preparation works for the closure.
The diversion routes would be sign posted via:
- Ring Road Weetwood, Ring Road Adel, Ring Road Meanwood, Ring Road Moortown, King Lane, Stonegate Road, Meanwood Road, Cross Chancellor Street, Melville Road, Woodhouse Street, Rampart Road and vice versa,
- Ring Road West Park, Ring Road Horsforth, Broadway, A65 New Road Side, Abbey Road, Kirkstall Lane, North Lane and vice versa.
Essential access for emergency vehicles will be maintained.
The location of the works is shown at link to https://one.network/?tmi=GB26549940