Major works are due to be carried out by Yorkshire Water in the Old Pool Bank area of the village. The latest details are shown below.
1 |
Old Pool Bank – Bottom Side |
Start Date |
End Dates |
10.06.2024 |
28.07.2024 |
TM |
Road Closure Old Pool Bank Bottom Side |
- Advanced Warning Signs issuing advising of road closure 2 weeks prior to works starting
- Letter drops to affected customers/residents on Old Pool Bank (bottom side from Junction Leeds Road down to Pool Bank New Road)- informing of closure/diversion
- 7 day working between 08:00-18:00
- Businesses and Dog park open as usual signs required – at junction Pool Bank New Road
2 |
Leeds Road/Junc Old Pool Bank to the junction of Quarry Road |
Start Date |
End Dates |
29.07.2024 |
22.09.2024 |
TM |
2 Way Lights |
- Letter drops to nearby customers on old pool bank/leeds road/quarry road.
- Advanced Warning Signs issuing advising of TM 2 weeks prior to works starting
- 7 day working between 08:00-18:00
- Social Media post targeting the area
3 |
Old Pool Bank – Top Side |
Start Date |
End Dates |
29.07.2024 |
20.10.2024 |
TM |
Road Closure Old Pool Bank Top Side |
- Advanced Warning Signs issuing advising of road closure 2 weeks prior to works starting
- Letter drops to affected customers/residents on Old Pool Bank (from Junction Leeds Road up to Quarry Farm road)- informing of closure/diversion
- 7 day working between 08:00-18:00
4 |
Quarry Road |
Start Date |
End Dates |
21.10.2024 |
03.11.2024 |
TM |
Road Closure of Quarry Road |
- Will speak to the properties impacted directly
- 7 day working between 08:00-18:00